How Long It Actually Takes

Every owner is told a number at the start and most projects take longer. The gap is usually permitting, long-lead items and decisions — rarely the building itself.

Bring the drawings at whatever stage they are. An honest range and the decisions that move it, before anyone quotes.

Licensed

General contractor, licensed in the state of Florida

Self-perform

Dewatering, SOE and deep foundations in house

Leadership

Delivered Fifth Avenue and Central Park West interiors

Open book

Where the contract is cost-plus, the books open

The schedule is not mostly construction

On a substantial custom home, actual construction is often the smaller share of the elapsed time. Design development, permitting, long-lead procurement and owner decisions consume the rest, and those are the parts most often compressed on paper because they feel like they should be quick.

Where the time actually goes

  • Design development and a genuinely complete construction set.
  • Permitting, which in some Florida jurisdictions is months.
  • Long-lead items: specialty windows, stone, millwork, elevators.
  • Owner decisions, which are the most controllable delay and the most common.
  • Weather and the wet season, which is a real program input here.

How we handle it

  1. 01Give a realistic program with the assumptions written down.
  2. 02Identify long-lead items early and order against the schedule.
  3. 03Set owner decision deadlines and report against them.
  4. 04Update the program honestly when it moves, rather than at the end.

Owner decisions are the delay owners have most control over and least visibility of. A selection made three weeks late does not cost three weeks — it can cost a trade sequence, which is considerably more.

Said plainly

Where we stop

If you have a hard date driven by a sale, a school year or an event, tell us at the start. Sometimes the honest answer is that the date is not achievable, and that is much better said in month one.

FAQ

Common questions

How long for a custom home?
Well over a year for a substantial house, often considerably more once permitting and long leads are counted.
How long is permitting?
Jurisdiction dependent and frequently months. It is a real line on the program, not an administrative afterthought.
What causes most delays?
Owner decisions and long-lead procurement, more often than trades.
Does the wet season matter?
For site work and the envelope, yes. It is planned around rather than ignored.

Next step

Find out what is actually wrong with it.

An inspection, photographs of what we found, and a written scope. If the honest answer is that it can wait another season, that is the answer you will get.